Crews and contractors continue to build better in-home internet from Wintek powered by Tipmont. Find your location, consult the color key, and find more details below if your area has a number.
- MANSON: We’re wrapping up construction and testing in both portions of this area and plan to open orders for service this month. Let us know you’re ready at wintek.com/getstarted.
- LAYTON: Construction is underway in the northern portion and kicks off later this month for the southern portion. In both portions, we’re scheduled to complete construction this summer. Register your interest with us at wintek.com/getstarted.
- WEA: The finishing touches on testing are almost done on 500 South between Concord Road and 450 East. We plan to open orders for service this month. Be among the first to get it and register at wintek.com/getstarted.
- MOUNTAIN ROAD: Engineering and pre-construction activity continues ahead of a three-phase construction scheduled to begin in May. Service orders should open in late summer/early fall. Make sure you’re on the list and register at wintek.com/getstarted.
- HILLSBORO SOUTH: Construction is slated to start in July with service orders available in the fall. Tell us you want better internet at wintek.com/getstarted.